Recoated Passenger Ferry Freed by Shipyard Crew

The M/V Kaleetan. Photo courtesy of Puglia Engineering, Inc.

As a scope, blasting and coating a car and passenger ferry might not sound like a challenging endeavor. But for Puglia Engineering (Bellingham, Washington), doing business as Fairhaven Shipyard with an 80- to 200-person yard, the details of the M/V Kaleetan project were complex.  

The 382-ft (116-m) long project included coating work on railings, bulkheads, decks, and rescue boat “pockets.” The recoat was to be done on steel and aluminum substrates. There was electrical and steel work, including a variety of tests. They had to work 24 hours a day, seven days a week, and they also had to overcome challenges with acquiring the amount of materials necessary. As if that wasn’t enough, they had exactly 92 days to complete the project.

“We’re a full-service shipyard,” says Dale Lockwood, senior project manager. They had the skills to complete the project, but could they overcome the choppy seas ahead?

The M/V Kaleetan, which means “arrow” in Chinook, was originally built in San Diego in 1967. To bring it back to its former glory, the crew (averaging 100 to 125 people) started with prep. After establishing blast and paint zones, they protected the wiring from grit blasting and overspray. They zoned and sealed the area and then covered the wiring with ~10 mi (16 km) of rubber strips. Only once covered could the blasting crew come in to work. 

Working in 100-ft (30-m) long sections, the Fairhaven Shipyard crew blasted to NACE No. 2/SSPC-SP 10, “Near-White Metal Blast Cleaning.” They wore blast hoods with fresh air and used four 8-ton (7,258 kg) blast kegs at 1,800 cfm (51 m3/min). Each of the blast kegs had four hoses. On the steel substrates, they used 36-grit copper slag. On the aluminum substrates, which included part of the Texas deck around the pilothouse and crew houses, the crew used 30/60 garnet. In areas where the blast hoses couldn’t reach, the 25-person blasting crew used power tools to achieve SSPC-SP 11, “Power Tool Cleaning to Bare Metal.” 

“After that, everything got cleaned up,” says Coatings Supervisor Benny Briones. They used vacuums for any spent slag or other debris and then sent the quality assurance (QA) team through. 

To keep QA, a foreign material exclusion team came in every four hours while the blasters were on break to inspect and repair any damaged wire protections. “And then we’d roll into painting,” Briones says.

With four sprayers and 200 ft (61 m) of line for each, the paint crew applied 3 to 4 mils (76 to 102 µm) of green primer to the steel substrates. At night, the crew reached 12 people and by day it hit about eight to complete touchups.

Once the primer was down, the crew covered the floors with paper, which would be receiving a special antiskid coating later. The coating systems also varied in type and color depending on the area of the ship. 

The bulkheads and overheads, for example, received 5 to 6 mils (127 to 152 µm) of marine epoxy in gray. Then a stripe coat was applied by hand as well as another 5- to 6-mil (127 to 152 µm) coat of the same coating in an off-white color. That was topped with a high-solids polyurethane at 2 to 3 mils (51 to 76 µm).  

When it was time to coat the decks, the eight-person antiskid crew came in to work. They applied the coating with phenolic rollers: an anticorrosive low-VOC metal primer in haze gray at 4 to 5 mils (102 to 127 µm), followed by a heavy-duty two-component anti-slip epoxy coating with Kevlar® in gray and safety yellow at 40 ft2/gal (1 m2/L). The aggregate used for the antiskid properties was integrated into the coating.

Another coating was used in the boat pockets that held the rescue ships as well as the marine evacuation system rescue slide areas. There, another coatings crew—from J. Calman Industries (Lynden, Washington)—applied two polyurea coatings: one at 80 to 100 mils (2,032 to 2,540 µm) and one at 10 to 20 mils (254 to 508 µm).

Throughout the coating application, Fairhaven Shipyard relied on QA after every layer as well as proper safety gear. Safety gear included full-face masks, hard hats, Tyvek® suits, and latex gloves. They also used wet film thickness gauges to ensure accuracy.

Between the coordination and materials, the scope of work on this project certainly gave the shipyard a run for its money. 

According to Lockwood, the crews “moved around” to allow the various crews to work simultaneously. “We’d blast really big areas, and then when we got that area blasted out and accepted by QA and the customer, the blast crew would take their equipment and move to another zone and the paint crew would move in,” he says.

With 125 crew members at the peak of the project, it was no wonder Briones relied on a production meeting at the start of every day. That allowed coordination to be clear between each of the different crews. 

“We had a real challenge with materials because nobody had recently seen a job that big done that quick,” Lockwood explains. “The purchasing unit had trouble getting the amount of grit and garnet that we needed.” But they managed by sourcing various suppliers nearby. In total, they consumed 1,000 tons (907 metric tons) of the coal slag, 100 tons (91 metric tons) of the garnet, and more than 5,000 gal (19 m³) of coatings. 

Before the M/V Kaleetan could pull out of port, the shipyard had to return the wiring back to its previous configuration and complete tests. “We’d find a stray cable somewhere that got nicked,” Lockwood explains. The 20-person electrical crew had to replace wiring, put panels back, and complete troubleshooting, “making sure every system was ready to go on day 92,” he continues.

Even up to the last day, the crew was on the ferry replacing stickers, safety signage, and deck markings. But after all that work, after 92 days and more than 200,000 ft2 (18,580 m²) of coated surfaces, Fairhaven Shipyard was able to cast off on time. Hopefully this was just the start to smooth sailing for the M/V Kaleetan!

This article, by Stephanie Marie Chizik, was condensed and reprinted with permission from CoatingsPro Magazine.